Skyline Drive Repaving

Talk about anything in this section, just keep it clean. :-)

Moderators: Mazdahead, Matt Rowe, Nelson

Skyline Drive Repaving

Postby Rich Rock » Thu Jul 30, 2015 3:11 pm

Maybe. Check out the article in today's paper. It's accurate up to a point. Its absolutely true, though, that the plan is to repave the entire length of the road if they get the grant. If they do get the grant, it probably won't get done until next year.

http://Www.readingeagle.com/news/articl ... line-drive
Rich Rock
Racer
 
Posts: 928
Joined: Tue Mar 30, 2004 7:56 pm

Re: Skyline Drive Repaving

Postby Rich Sweigart » Fri Jul 31, 2015 4:48 pm

Happy for the paving, not to happy about rumble strips. Is there anyway we can have them removed from the plan? Rt 202 bi-way thru Montgomery and Bucks Counties has bikes lanes on it with nothing but, a normal white line separating the travel lanes and the bike lanes with a token bike symbol painted in the bike lanes.

ps Love the photo used by the Reading Eagle, someday I will find time to install a new gas tank in the 924. :mrgreen:
Rich Sweigart
Rich Sweigart
Novice
 
Posts: 390
Joined: Sun Mar 21, 2004 12:20 pm
Location: Quakertown, PA

Re: Skyline Drive Repaving

Postby Rich Rock » Sun Aug 02, 2015 6:17 am

There will be rumble strips, no way to have them removed from the plan. They will not necessarily be installed the entire length of the project, there will likely be some gaps. The location and length of those gaps is yet to be determined. Stay tuned, but don't expect any news real soon. This stuff takes time, lots of time.
Rich Rock
Racer
 
Posts: 928
Joined: Tue Mar 30, 2004 7:56 pm

Re: Skyline Drive Repaving

Postby offy255 » Mon Aug 03, 2015 5:49 pm

Today's Reading Eagle Letters to the editor
Attachments
Scan0009.jpg
offy255
Novice
 
Posts: 72
Joined: Wed Aug 23, 2006 6:39 pm
Location: Reading Pa.

Re: Skyline Drive Repaving

Postby Rich Rock » Fri Jul 01, 2016 5:17 pm

The grant has been approved!! Looks like it's gonna happen, but not before this year's Duryea.

Stay tuned for details, but be patient. Like I said before, this stuff takes time.
Rich Rock
Racer
 
Posts: 928
Joined: Tue Mar 30, 2004 7:56 pm

Re: Skyline Drive Repaving

Postby Mark Aubele » Sun Jul 03, 2016 10:45 pm

Last year to set records without the excuse of having a freshly paved road!
'14 Mustang ESP #53
Mark Aubele
Novice
 
Posts: 226
Joined: Wed Jul 26, 2006 12:22 am
Location: Trafford, Pa

Re: Skyline Drive Repaving

Postby Rich Rock » Sun Apr 23, 2017 3:20 pm

The contract has been awarded, and preliminary work has begun! The actual repaving work is scheduled to begin the second week of May.
Rich Rock
Racer
 
Posts: 928
Joined: Tue Mar 30, 2004 7:56 pm

Re: Skyline Drive Repaving

Postby Rich Rock » Sun Jun 04, 2017 7:53 pm

The work is moving along. I was up there today and can report that the milling of the road and the laying of the base coat of asphalt from just above the Pagoda, continuing past the tower all the way to List Road (Duryea turnaround) is done. I took a couple pictures but I've never been able to figure out how to attach a picture. So, for now I'll just say that it's looking good!